What began as a simple request – setting up views for the tender stage of a Student Accommodation Development Application (DA) – evolved into a two-year engagement. Our team supported the project from DA through to Construction Documentation, delivering accurate, compliant outputs while integrating consultant designs.
As complexity grew, the value of a dedicated remote team became clear. With deep project knowledge, our team maintained quality and momentum, managing design development, adapting to consultant inputs, and keeping the documentation package on track.
Technical challenges that demanded a new approach
Complex stakeholder coordination
This was a dynamic consultant environment, with multiple specialists joining mid-project and introducing new requirements. Direct builder oversight added complexity, demanding that construction priorities be met without compromising design intent. Our dedicated remote team adapted quickly, incorporating changes and keeping documentation aligned with project milestones.
Modular facade innovation
One of the project’s defining features was its modular facade system. Chosen for its ability to streamline fabrication and installation, the approach required precise documentation that could be translated directly into manufacturing outputs.
By breaking down the facade into standardised, repeatable modules, we reduced complexity during both the design and build phases. This method minimised on-site adjustments, improved installation accuracy, and allowed fabrication to run in parallel with other construction activities, compressing the build schedule and improving cost certainty.
Automation through Dynamo scripting
The scale of the project meant manual updates across hundreds of drawings would have been resource-heavy and prone to error. To solve this, our team developed custom Dynamo scripts to automate repetitive documentation tasks, from content generation to bulk parameter updates.
This automation significantly reduced manual effort, improved accuracy, and cut turnaround times for design revisions. The result was faster delivery, fewer coordination errors, and measurable cost savings across the documentation phase.
Navigating ongoing design changes
On this build, design changes were a constant challenge: driven by compliance updates, shifting stakeholder priorities, and evolving construction methodologies.
Every change request was assessed in context, its impact on other disciplines, its effect on sequencing, and its alignment with compliance requirements before being actioned in the model, and we were able to do this without losing momentum.
By applying a structured review process, we reduced the risk of late-stage rework, avoided costly site delays, and ensured that every update was tracked through the project’s lifecycle.
Balancing speed with precision
Meeting deadlines on a complex build meant working fast – but never at the expense of quality. With hundreds of drawings and model updates in play, even a small mistake could ripple across trades and cause costly delays.
To manage this, we combined modular design principles, BIM coordination, and Dynamo automation to create a workflow where speed and accuracy worked hand in hand. Regular model audits and clash detection reviews kept errors out of the construction phase. The modular façade approach added further certainty – once a unit was validated, it could be repeated with confidence, eliminating the need to recheck every iteration.
This approach kept delivery on track while ensuring the documentation remained accurate, coordinated, and build-ready.
A delivery model built for scalability
What began as a relatively contained engagement ultimately became a multi-year delivery partnership, scaling resources up and down as the project required. By working as an extension of the practice’s in-house team, we provided the flexibility to add capacity when documentation demand spiked and streamline back to core resource levels when volumes eased.
This scalability meant the project avoided the costly cycle of short-term hiring and onboarding, while maintaining continuity in both personnel and quality. The same Away Digital professionals who joined in the early phases were still contributing at completion, retaining the knowledge that’s so often lost in long projects.
Lessons for future large-scale builds
This project reinforced that the real value of a dedicated remote team isn’t just in meeting deadlines and delivering quality project documentation outcomes, it’s in derisking delivery. By working in accordance with our client’s systems, applying modular and automated processes, and maintaining consistent teams, we created a delivery environment that could absorb change without compromising quality or program.
Conclusion
At Away Digital, our role goes far beyond producing documentation. We build integrated partnerships that give project teams the flexibility, and stability they need to deliver complex builds successfully.
On this project, our approach helped transform shifting requirements and technical challenges into opportunities for innovation, proving that with the right combination of technology, process, and integration, even the most complex delivery environments can be managed with confidence.
In AEC, “dedicated team” is a term that gets thrown around without much clarity. It’s frequently mistaken for a quick fix, plugging gaps with short-term providers or task-based outsourcing. But a true dedicated team is built differently. They don’t disappear when a project ends, they embed into your workflows, scale with your capacity, and give […]
Burnout isn’t a buzzword. It’s one of the most pressing challenges facing architecture, engineering, and homebuilding firms. As demand rises and timelines tighten, internal teams are expected to do more with less, leading to overwork, high attrition, and constant recruitment cycles. But what if retention wasn’t just a culture or hiring problem? What if it […]
Great design is thoughtful. Intentional. Built to solve problems today while anticipating the needs of tomorrow. It’s a mindset most AEC leaders already apply to projects, but it’s just as powerful when applied to how teams are structured. However, it’s easy to fall into reactive resourcing, hiring under pressure, stretching your team, or leaning on […]
LET’S TALK
Subscribe to monthly newsletter
Sign up to receive a monthly email on the latest updates, features, and news!